Czech Dukovany Nuclear Plant Construction Contract Talks Collapse... KHNP Cites "Over 1 Trillion Won Increase Demand," Plans New Bid for Domestic Construction Firms

Negotiations on the construction contract for the Czech Dukovany nuclear power plant have been terminated. Korea Hydro & Nuclear Power (KHNP) cited the consortium of Daewoo Engineering & Construction and Doosan Enerbility's demands for changes to contract conditions and increased project costs as th

Wooil Shim
Staff Reporter
12 min read
Czech Dukovany Nuclear Plant Construction Contract Talks Collapse... KHNP Cites "Over 1 Trillion Won Increase Demand," Plans New Bid for Domestic Construction Firms
CBC News

Negotiations on the construction contract for the Czech Dukovany nuclear power plant have been terminated. Korea Hydro & Nuclear Power (KHNP) cited the consortium of Daewoo Engineering & Construction and Doosan Enerbility's demands for changes to contract conditions and increased project costs as the main reasons for the breakdown of negotiations. KHNP plans to wrap up talks with the existing consortium and pursue a new bid targeting domestic construction companies.

According to explanations from KHNP and the Ministry of Trade, Industry and Energy relayed by Yonhap News Agency on the 29th, the Czech nuclear project had been pursued on a lump-sum fixed-price basis from the initial bidding stage.

Disagreement over lump-sum fixed-price method... "Demands for increase exceeding 1 trillion won"

KHNP explained that the client requested a lump-sum fixed-price method at the initial bidding stage, and both KHNP and the Daewoo Engineering & Construction consortium agreed to it. Accordingly, the same method was applied in the initial bid in 2022 and the revised bid in 2023, and KHNP maintains that it also proposed the lump-sum method in 2023.

However, according to KHNP, Daewoo Engineering & Construction later conveyed that it would be difficult to maintain the existing lump-sum method, requesting a change to a system in which costs for additional construction work would be settled separately. KHNP explained that it judged these demands difficult to accept and submitted its final bid to the Czech side while maintaining the existing lump-sum method.

The scale of the requested project cost increase also emerged as a point of contention during negotiations. KHNP stated that while it is difficult to disclose the specific amount demanded by the consortium, it exceeded 1 trillion won. The demand went beyond what KHNP could bear, according to the explanation.

However, this is KHNP's account of the background of the negotiations' collapse. The Daewoo Engineering & Construction and Doosan Enerbility consortium is disputing the process of the termination. The consortium previously stated that KHNP changed contract conditions just before the talks ended and did not provide sufficient time for review, and that it cannot accept the unilateral termination of negotiations.

Ministry of Trade, Industry and Energy "Respects KHNP's judgment"... Communicating with Czech government since February

The Ministry of Trade, Industry and Energy expressed its respect for KHNP's decision to end negotiations. Kim Chang-hee, Director-General for Nuclear Power Policy at the ministry, said a final decision had to be made by the 29th to ensure timely completion, and that the government respects KHNP's judgment. He also said government-level support would continue during the process of selecting a new contractor.

Consultations with the Czech government are also underway. Director-General Kim said he has been communicating with the Czech government in real time on related matters since February. He explained that at the Dukovany implementation review committee (DSC) meeting held last week, the government conveyed its plan to reach a certain conclusion within October. He noted that the Czech side's basic demand is to proceed with the nuclear project according to the scheduled timeline.

"No large nuclear plant construction for 15 years after Wolsong"

KHNP said it also reviewed the existing consortium's nuclear construction experience and the issue of securing specialized personnel during negotiations. The Daewoo Engineering & Construction consortium was selected after receiving good scores in the 2018 evaluation, but KHNP said it re-examined the consortium's nuclear construction experience and personnel situation afterward. In particular, it mentioned that Daewoo Engineering & Construction had not carried out a large nuclear plant construction project for about 15 years since the Wolsong nuclear power plant.

KHNP also stated that the consortium's request to change requirements related to securing experienced specialized personnel demanded by the client influenced its decision.

New bid announcement in March-April 2027... Contractor selection by July of the same year

KHNP plans to conduct the new contractor selection process centered on domestic companies. The new bid will be announced in late March or around April 1, 2027, with contractor selection to be completed by July of that year. KHNP said it has no plans to open the new bid to foreign companies and will select a contractor through the participation of domestic construction firms.

The possibility of legal disputes also remains. KHNP acknowledged the possibility that the Daewoo Engineering & Construction and Doosan Enerbility consortium could file a lawsuit over the termination of negotiations, but said it will proceed with the new bidding process. However, it did not definitively state that legal disputes would have no impact on the project schedule.

KHNP plans to itemize the work that the existing consortium was supposed to carry out and proceed with tasks it can handle directly on its own. It is also reviewing plans to push forward some tasks needed in the early stages through separate contracts.

With this termination of negotiations, the Czech Dukovany nuclear plant construction project now faces a new contractor selection process. Going forward, the new bid schedule, whether the existing consortium will take legal action, and the two sides' differences over contract conditions are expected to remain key issues in the project's implementation.

[The content regarding the changes to contract conditions and project cost increases reflects KHNP's explanation and does not represent facts confirmed by legal judgment or final agreement between the parties. AI assistance was partially used.]