Camu E&C Wins 195.7 Billion Won PC Construction Contract for SK Hynix Yongin Cluster, Equivalent to 65.8% of Recent Revenue
Camu E&C announced that it has signed a contract worth 195.679 billion won with SK Ecoplant for the 'SK Hynix Yongin Cluster Phase 1 Ph-4 IBL FAB PC Construction' project. ■ 65.8% of Recent Revenue... PC Material Supply and Installation for FAB Zone 2 According to the regulatory filing, the contra

Camu E&C announced that it has signed a contract worth 195.679 billion won with SK Ecoplant for the 'SK Hynix Yongin Cluster Phase 1 Ph-4 IBL FAB PC Construction' project.
■ 65.8% of Recent Revenue... PC Material Supply and Installation for FAB Zone 2
According to the regulatory filing, the contract amount of 195.679 billion won excludes value-added tax and equals 65.8% of the company's recent revenue of 297.453 billion won based on the consolidated financial statements for the end of fiscal year 2025.
The scope of the work covers the supply and installation of precast concrete (PC) materials for FAB Zone 2 within the SK Hynix Yongin Cluster Phase 1 Ph-4 IBL construction project. The region of sale and supply is Yongin, Gyeonggi Province.
■ Contract Period from August 27, 2026 to May 31, 2028... Interim Payment Terms
The contract period runs from August 27, 2026 to May 31, 2028. The contract date is August 31, 2026, based on the date of the counterparty's electronic signature. There is no contract deposit or advance payment, and payment will be made on an interim (progress-based) basis.
■ What Is the PC Method?... An Industrialized Construction Method Involving Factory Production and On-Site Assembly
Camu E&C explained that the Precast Concrete (PC) method is part of off-site construction (OSC), an industrialized construction approach in which concrete structural elements such as columns, beams, and slabs are manufactured at a factory and then transported to the construction site for assembly.
The company also noted that the contract amount and period may be subject to change as the construction progresses.
CBC Globe publishes verified stories with editorial review, source checks, and tenant-specific publication standards.

![[Breaking] Onconova Cross Signs ADC·BsADC Co-Development Contract with Aptis…Contract Fee and Milestones Total 2.8 Billion Won](/_next/image?url=https%3A%2F%2Fmedia.cbcglobe.com%2Ftenants%2Fcbc00000-0000-4000-8000-000000000001%2Fmedia%2Fcbc%2F2026%2F08%2F597362%2Fbc89c68a76bf51cc%2Fvariants%2Fhero.webp&w=1920&q=75)

![[Breaking] Bukwang Pharm Shares Surge Over 9%... Static VI Triggered and Quickly Lifted in Afternoon Session](/_next/image?url=https%3A%2F%2Fmedia.cbcglobe.com%2Ftenants%2Fcbc00000-0000-4000-8000-000000000001%2Fmedia%2Fcbc%2F2026%2F08%2F601702%2F849e33f3e55ed1c6%2Fvariants%2Fhero.webp&w=1920&q=75)